Construction work on the Red Line Bus Rapid Transit (BRT) project Lot 2 on Karachi’s University Road has resumed, with Frontier Works Organisation (FWO) taking over development on a key section of the route, officials confirmed on Sunday.
The development was also confirmed by Sindh Chief Minister Murad Ali Shah during a site visit to the under-construction corridor.
He expressed regret over the difficulties faced by citizens due to ongoing work on University Road and said the government takes full responsibility for the inconvenience.
“I apologise to the citizens affected by University Road construction. We will try to compensate for the hardship faced by Karachi residents. I have taken responsibility,” he said while speaking to a private TV channel.
Visit Times of Karachi website for the latest news-related content
The Chief Minister thanked the Frontier Works Organisation (FWO) for taking over the project and said that visible construction activity would begin within two to three days.
He further announced that the main corridor of Lot 2 would be retendered and expressed hope that the mixed traffic lanes would be completed within two to three months.
“People do not know the contractor; they know the Sindh government,” he said, adding that the earlier contractor was awarded the project four years ago but failed to meet quality standards.
Murad Ali Shah also directed that construction work should continue even during Eid holidays to avoid further delays.
Also Read:
Karachi development projects to finish by June 30: Mayor
The move comes after authorities cancelled the previous contractor’s agreement due to repeated delays and unsatisfactory performance.
TransKarachi officials earlier stated that concerns raised by the Asian Development Bank (ADB) over progress, safety standards, and environmental compliance also contributed to the decision.
Background of Karachi Red Line BRT project:
The Karachi Red Line BRT project, launched in 2022, was originally scheduled for completion by June 2024 with a 30-month timeline. However, repeated delays – especially in Lot 2 – have pushed the project beyond its deadline.
The route is divided into two sections: Lot 1 (Airport to Mosamiyat) and Lot 2 (Mosamiyat to Numaish), with the latter experiencing major execution problems.
Ongoing construction has also caused traffic congestion and disruption for residents across the city.
About FWO:
The Frontier Works Organisation (FWO) is one of Pakistan’s leading engineering and construction organizations, known for its role in large-scale infrastructure development projects across the country.
FWO built a strong reputation for delivering complex engineering work in challenging environments. Over the years, FWO has been involved in road networks, bridges, tunnels, dams, and urban development projects.
Follow the Times of Karachi channel on WhatsApp
In recent times, FWO has also played a key role in major urban transport initiatives, including metro and Bus Rapid Transit (BRT) systems. Its involvement is often sought when projects face delays or require rapid completion due to its technical capacity and organized execution structure.
In Karachi, FWO has recently been assigned work on sections of the Red Line BRT project, where it is expected to accelerate construction and help address long-standing delays in the system.
Overall, FWO is considered a key institution in Pakistan’s infrastructure development landscape, contributing to both national and urban-level engineering projects.