A new completion deadline has been set for the long-delayed Munawar Chorangi Underpass project in Karachi, as city and provincial leadership push to finish the long-delayed infrastructure scheme.
The update was shared after Mayor Karachi Murtaza Wahab visited the project site along with CM Sindh Murad Ali Shah and Local Government Minister Syed Nasir Hussain Shah on May 3, 2026.
Visit Times of Karachi website for the latest news-related content
Mayor Karachi on his social media post announced that the Munawar Chorangi underpass is now expected to be completed by June 30, 2026.
Happy to share and announce that CM has directed that work on the Munawar Chowrangi Underpass in Gulistan e Johar be completed by 30th June. All funding will be provided to ensure its completion within the said timeline #KarachiWorks #HamaraShehar pic.twitter.com/1zfNz22Esf
— Murtaza Wahab Siddiqui (@murtazawahab1) May 3, 2026
Following the visit, the mayor stated that the chief minister had directed authorities to ensure completion within the revised timeline, adding that all necessary funds would be made available.
Also Read:
“Financial Constraints, Design Delays main reason for Red Line BRT Slowdown, claims Ex-Contractor
The Munawar Chorangi Underpass, located in Gulistan-e-Johar, was launched in 2023 with an allocated budget of Rs2.02 billion. The project aims to ease traffic congestion in one of Karachi’s busiest corridors.
Despite initial targets, progress has been slower than expected.
Follow the Times of Karachi channel on WhatsApp
During a high-level meeting on February 24, 2026, chaired by the chief minister to review Karachi’s development projects for the 2025–26 financial year, a one-month completion deadline was set; however, it was not met, and a new deadline has announced by Mayor Murtaza Wahab.
During the same meeting the CM was told that the government has released Rs300 million to support ongoing work at Munawar Chorangi, with construction continuing at an accelerated pace.