The Sindh High Court (SHC) on Thursday ordered Sindh’s Energy and Irrigation departments to give details on the Thar Coal water supply project.
Enayat Ali Mirza, the petitioner, asked the court to require the irrigation and energy agencies to give information regarding the project under the statute governing access to information.
The court directed the government departments to give the petitioner with a copy of the challan if any legal charges were necessary.
It is a pipeline project for 50 cusecs water delivery from Nabisar to the Thar Coke facility, according to the petitioner. “After tremendous expenditure of 66 billion rupees, the project has remained unfinished,” petitioner’s attorney stated.
“Applications were given to Sindh’s Secretary Irrigation and other officials under the access to information law but none of them have been ready to provide correct information,” Zafar Ali advocate said.
“Rs 30,000 were demanded after offering photostat copies,” petitioner’s lawyer said. “We are ready to pay the amount, but they are not issuing copy of the payment challan,” he added.
Superintendent engineer of Thar Coal Waterworks project Waqar Qadri, talking to ARY News in last year June said that the project will be completed with 30 billion rupees cost. It will supply water with 61.7km long water pipeline, he added.
It is to be mentioned here that the Sindh government had signed a Rs30.1 billion 25-year concession agreement with a Kuwaiti state-owned company, for provision of 45 cusecs of water through a 61km pipeline from Nabisar to Vajihar.
The Nabisar-Vajihar pipeline will supply water to Thar power projects. The water supply project would ensure the supply of industrial water to coal-based power sector.
The project is expected to be completed within 12 months.
Sindh Chief Minister Murad Ali Shah in last year June laid foundation stone of the water supply scheme in Thar.