Shahrah-e-Bhutto Corridor from Karachi Port to Qayyumabad approved

Stay updated - Follow TOK on WhatsApp for instant alerts!
Sindh’s PPP Policy Board has approved a 16.5-kilometre, four-lane Shahrah-e-Bhutto corridor linking Karachi Port with Qayyumabad.
The project contract will span 27.5 years, including 2.5 years of construction, and is planned under a design, finance, construction, operation and transfer model.
The board also approved riverbank protection works and additional infrastructure at the Memon Goth Interchange.
0:00 / --:--
Advertisement

The Sindh government has approved the construction of a new corridor of Shahrah-e-Bhutto, connecting Karachi Port with Qayyumabad, as part of plans to improve road connectivity in Karachi.

Follow Times of Karachi on Google News and add as a preferred Source on Google

The approval was granted during a meeting of the Public-Private Partnership (PPP) Policy Board chaired by Sindh Chief Minister Murad Ali Shah.

The proposed 16.5-kilometre expressway will have four lanes and extend from Karachi Port to Qayyumabad. According to a briefing presented to the board, the road will also connect with the East Wharf of Karachi Port.

Project to be developed under PPP model

The project will be carried out under a public-private partnership arrangement, with the contract covering a total period of 27.5 years.

The contract period will include 2.5 years for construction, according to the briefing.

The corridor is planned on a design, finance, construction, operation and transfer (DFBOT) basis. Under this model, the private partner is expected to be involved in designing and financing the project, carrying out construction and operating the facility before its transfer.

Advertisement

The meeting also discussed a proposal to introduce an “infrastructure right” in place of equity as part of the project’s financing structure.

KPT licence agreement and final NOC discussed

The PPP Policy Board also discussed matters related to the Karachi Port Trust (KPT) licence agreement and the issuance of the final no-objection certificate (NOC).

The proposed connection between Shahrah-e-Bhutto and Karachi Port’s East Wharf is expected to provide a direct road link between the port area and Qayyumabad.

Further details about the project’s construction schedule, financing arrangements and final approvals were not provided in the briefing.

Riverbank protection and Memon Goth interchange works approved

In addition to the corridor, the board approved works aimed at protecting riverbanks along the Shahrah-e-Bhutto expressway.

Advertisement

The meeting also approved the construction of a protective embankment, an additional loop and a ramp at the Memon Goth Interchange.

The installation of streetlights at the interchange was also approved.

The decisions form part of the broader project plan for Shahrah-e-Bhutto, which is intended to improve road infrastructure and connectivity in Karachi.

Share

Follow Times of Karachi on Google News and explore your favorite content more quickly!
Leave a Reply
Related Posts
Prime Minister's Youth Chromebook Scheme
🚫 Ad blocker detected. Please disable your ad blocker to support our content.
Close Button
Advertisement